My teams estimate work based on story points. However, people can only log work in Weeks, Days, and hours. Is there a way to configure JIRA to allow work to be logged in story points?
Community moderators have prevented the ability to post new answers.
No, because they're measuring different things. Story points are a measure of complexity, and work-logs are about elapsed time. Unless you make a (false) equivalence such as "1 SP = 1 hour", which means you might as well just use the time logging.
Have a look at why over at https://www.atlassian.com/agile/estimation
Hi Nic,
I understand the need to use story points as a measure of complexity. If we do use time tracking (as the management is constantly asking how we are doing in relation to budgets), how do we show burn down or velocity in relation to time tracked?
Thanks in advance and apologies for posting variations of this question in other places.
Eshan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, I am facing same issue. did you get the resolution? How did you manage to get the reports then?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.