For the Gantt Chart View, is there a way Issue Dates can be automatically recalculated based on the Start date of a linked task?
While I can manually move the task, it would be a lot more effective if I could recalculate the dates for the tasks.
Community moderators have prevented the ability to post new answers.
This feature was added as part of 2.9.1 and is working great for me!
Thanks but it's still not available in Atlassian marketplace, the latest available one is 7.2.4, when can this be expected.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
BigPicture currently does not offer this feature, but it has been requested and not only is in development - actually it is already in the testing phase, and should be out in (give or take) a week! So please stay tuned
More details here: https://softwareplant.eu/jira/browse/BIGPICTURE-497
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.