Rick Burge November 29, 2017

If I enter 8h for a task estimate it converts and displays as 1d 1h (because available hrs is 7). I just want it always to show hours - 8h.

Capture.JPG

 

Thx

Rick

1 answer

Suggest an answer

Log in or Sign up to answer
1 vote
Carlos Garcia Navarro
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 10, 2017

Hi Rick,

From the JIRA Admin cog-> Issues-> Issue Features > Time Tracking, you can change the time display format, as shown in this picture:

Screen Shot 2017-12-10 at 9.44.33 PM.png

Hope it works,

Carlos

Rick Burge December 11, 2017

Carlos,

 

Thx for the reply. Yes that was exactly what I was looking for. Might clarify though that you have to Deactivate the Time Tracking in order to see the screen you presented. Once I figured that out worked like a champ.

Thx

Rick

Carlos Garcia Navarro
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 11, 2017

I'm glad it worked!