We use Jira Agile with Scrum but estimate with Time. The documentation says time based estimation only works with Kanban but I wanted to check to see if it can be done with agile as well.
Yes you can. In the configuration of your plan, you decide which estimation method to use for your plan:
As you can see from the screenshot, planning units are Days / Hours or story points.
you can find the setting by clicking the 3 dots [ ... ] next to your plan's name. This will bring you to the configuration pages. Planning mode is under PLANNING / Scheduling