Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,459,905
Community Members
 
Community Events
176
Community Groups

how can I see the total capacity of a member who is in many projects

I have to configure my portfolio like this: 

Note

If you have a member on more than one team, then add that individual to all relevant teams and distribute their weekly hours to proportion their effort between teams. Also note that adding team members is not necessary since you can easily plan with team velocity.

 

But I don't find where I can see the capacity of a member which is distribuited between many projects and also, I don't find where I can change the hours per project of each member.

1 answer

0 votes
Raathi Atlassian Team Aug 17, 2018

Hi Ana,

Have you tried the capacity report ? You can filter the details by teams or members, to see the specific capacity of each individual.

To change the hours per project of each member, please refer the To configure weekly hours of a team member section from configure team settings.

Regards,
Raathi

Hi Raathi,

I did it! Finally I found it! Thank you Raathi. Although now I have another problem. There is a way to see if a team member has more weekly hours than total allowed between projects? And the most important question, can you add a project in a plan when the plan has already created?

 

THANK YOU AGAIN,

Ana

Raathi Atlassian Team Sep 13, 2018

Hey Ana,

Sorry for the late reply.

You can edit the issue sources and bring a new project into the plan. 


There is a way to see if a team member has more weekly hours than total allowed between projects? 

I'm not aware of it. I'll check on it.

Regards,
Raathi