Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Target Date on Portfolio plan

GetConnected Atlassian Support November 26, 2018

Hi all,

I'm trying to add in my scope view target start and target end field but they disappear everytime I  make a calculate. 

In the target schedule I can't see my baseline. 

Did you ever had the same problem? 

1 answer

0 votes
Susete Alves Eccher October 11, 2019

I think this happened when there is estimate, in which case the Portfolio does not consider the informed dates but recalculates.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events