Syncing story point sum from JIRA Portfolio to JIRA

Bernhard Böhmer October 13, 2018

Hi,

we suffered a problem in the interaction between Portfolio and JIRA:

We are exclusively calculating story points in the scope view of Portfolio using the Story Point settings there. The story points are nicely summing up but (after committing the changes) don't seem to by synced with JIRA Core. Thus, they are not shown at the boards. This breaks the usage flow at JIRA Core.

My expectation would be that the story point sum in portfolio would show up in the default story point field in JIRA Core.

Is that something already being addressed?

    Thanks Bernhard

1 answer

0 votes
Mohamed Riza
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 14, 2018

Hi @Bernhard Böhmer

The story point changes made in Portfolio does show up on the issues in Jira, however, this needs to first be committed from Portfolio. The commit option would show on the top left of the plan once the changes are made to the Story point on the plan. 

Bernhard Böhmer October 15, 2018

Hi Mohamed,

I've indicated that the commitment were done. I will collect further indications and follow up.