Release fixed start and end dates have changed

Hello,

 

I am trialling Portfolio as we hope to utilise it for our resource planning. I currently have two projects showing in Portfolio and am happy with the scheduling so i have applied fixed start and end dates to all the Releases associated with the two projects.

I have now introduced a third project, but rather than scheduling the work around the committed workload and dates for the first two projects, it has changed the fixed Release dates assigned to the second project - the fixed Release dates for the first project that I introduced remain unchanged (Note: The only difference between the first and second project is the first project has dependencies from start to finish, where as the second project only has dependencies for the the first half of the project).

Why have the fixed Release dates for the second project been changed now I have introduced a third project? Do the fixed dates not necessarily mean they cannot be changed?

Best regards

Adam

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,586 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you