Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,456,991
Community Members
 
Community Events
176
Community Groups

Portfolio version 2, plan does not show completed stories

Edited

I am trying to look at the progress at Epic and intiative level,  But when I creata a plan , it does not show stories that are completed thus prrogress bar shows 0 progress.  

Anyone could help, perhaps I ma configuring something wrong

 

1 answer

0 votes
Thomas Atlassian Team Aug 20, 2017

Hi @Reza Montazeri,

 

There is a filter allowing you to decide how far to go look for completed items. For this, have a look at the "More" dropdown in the plan filter bar and select the "Completion Date" filter. You should then be able to specify the desired range.

If you are working with hours instead of story points, the progress is based out of logged hours which you might or might not use.

 

Cheers,

Thomas