Probably a silly question, but anyway:
I defined 6 sprints in my board.
Portfolio is set on that board.
I see the first three sprints in Portfolio - this is fine.
I want to see the later 3, but I can't find a way to scroll or zoom the timeline to get to them.
Any ideas? Thanks!
Hi Ofer
Do you happen to have estimates on the later Sprints that aren't displaying? They won't display if there aren't estimates on them.
Regards,
Shannon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.