I would like to see release/ Epics predictability based on three scenarios Standard, worst and best or something similar. Has anybody tried forecasting similar way
Hi Ashish,
I am not aware of any method or add-on that could provide an automated method to achieve a multi scenario approach or best to worst case timelines; but for a manual approach you can look into setting up Multiple scenario planning, and in each of the scenarios adjust the weighted items of the scheduling factors (i.e. rank, estimates, capacity, dependencies, etc...) to get the varying level of comparison, best to worst on the plans layout, and after reviewing commit the one that looks to be the most achievable.
Using this approach as your primarily looking at the Release variable you could set up one scenario with a "As early as possible" start date and a "dynamic" release date and the second with the optimal fixed dates and the third with a conservative fixed dates to compare the three variable plans and see if there are any conflicts in the schedule on each scenario.
Also check out the documentation for "Scheduling behavior" that goes into more detail on how the item weighted items are calculated.
Regards,
Earl
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.