Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,463,448
Community Members
 
Community Events
176
Community Groups

Jira Portfolio: Ranking at highest level instead of lowest?

My teams use JIRA to plan their projects. I want to be able to get the story point roll up but have the auto scheduler use the ranking done at a Milestone level (which is what I am using to track projects). Currently my #1 milestone gets pushed out and it appears to be b/c of the ranking of the stories beneath.  

1 answer

That is correct.  Stories take precedence over Epics over Parents.  Here's a good article on it that I just reviewed today.  I'm deathly afraid of auto-scheduler until I fully get results that I'm expecting.

 

https://confluence.atlassian.com/advancedroadmapsserver/auto-scheduling-issues-967895245.html#:~:text=Auto%2Dscheduling%20a%20plan&text=Above%20the%20timeline%20section%20of,is%20suggesting%20for%20your%20plan.

Thanks Chris, We are wanting to do this for high level multiple system Portfolio planning I think I might just need to do the work of adding the Story Points in manually :(. 

You can always select all of the children of the milestone and then change the rank to the top in bulk.  Then do the same for the next milestone and move them to "below issue 'Milestone#1'). That way your stories will all be assigned in priority based on milestone. And the auto-scheduler should assign them first.  But, I haven't tried it out yet.