We created a hierarchy on JIRA Portfolio with Objective -> Program -> Initiative -> Epic -> Story/Task.  The dates on Stories are correct and are being pulled in from the Sprints which populate Target Start and End Dates on Stories.   However the dates on the Epic, Initiative, Program and Objective levels are not being populated correctly from the stories.  The Target Start Date and Target End Dates are not using the first date for the Target Start Date and last date for the Target End Date from the stories.

2 answers

1 accepted

0 votes
Answer accepted
Dave Atlassian Team May 05, 2021

Hi @David Lam,

What version of Advanced Roadmaps / Portfolio are you using? The ability to roll-up dates wasn't available in all versions to you might need to upgrade to take advantage of this capability. It also needs to be enabled in the plan settings,

Regards,

Dave

It should be the most recent version 

Portfolio for Jira - 3.29.7

 

I already enabled it and the roll up is working for Epics just not the hierarchy above.  Epic to Initiatives,  Initiatives to Programs and Programs to Objectives are not working for rolling up the dates. Initiatives, Programs, Objectives do not have the inherited dates icon with the arrow.

Like Dave likes this
Dave Atlassian Team May 05, 2021

Thanks for confirming the version @David Lam, that sounds concerning - this might sound like a stupid question, but can you also confirm that the parent link is correctly set between those epics and initiatives?

Also, the inherited date won't show up in the same way that the sprint inferred dates do ... it will actually show up as a roll up symbol, see this screenshot for an example:

Screen Shot 2021-05-06 at 9.39.22 am.png

I'm guessing this isn't what you're seeing? The striped issue bars indicate that the dates are rolled up.

Regards,

Dave

1 vote
Curt Holley Community Leader May 05, 2021

Are your Epics, Initiatives, Programs and Objectives in the sprints, or just the stories? As I believe the "roll-up" of dates comes from the Sprint dates, not the children. Thus, to inherit the dates (where blank) they would have to be in the sprint.

The Epics, Initiatives, Programs and Objectives are not in the Sprints.  I got Epics to work it looks from the Stories. But Epic to Initiatives,  Initiatives to Programs and Programs to Objectives are not working for rolling up the dates.  Initiatives Programs, Objectives do not that the inherited dates icon with the arrow.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Jira

Do you use Jira Cloud with Microsoft Teams?

Hi, Jira users! Do you use Jira alongside Microsoft Teams? We want to hear how you’ve used the power of Jira Cloud and Microsoft Teams (via the Jira Cloud for Microsoft Teams app) to achieve a team...

470 views 3 7
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you