When evaluating the summary of hours from JIRA Portfolio the hours remaining add up to a considerable higher number than the numbers that show when I manually go into each story and add up the remaining hours. I've cleared my Cache as I believe Atlassian has said this sometimes can be an issue but if others have experienced this please advise.
Hi Kevin,
I checked internally and I could find that you raised a ticket for the support and it was answered there.
I'm posting the answer here, so others can use it.
Using example with issue
If you select the issue FPDSC-1047 estimation, you will see 81+90.
81 is the sum of all sub-tasks, 90 is the number of hours associated to the issue FPDSC-1047.
If you open the issue FPDSC-1047, you will see that this issue have no estimation in hours, but 15 story points.
Checking your plan issue source, 1 Story point = 6 hours, so the issue FPDSC-1047 have 90 hours estimated.
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.