Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage
  • Community
  • Products
  • Jira
  • Advanced Roadmaps
  • Questions
  • In JIRA Portfolio, when multiple teams are added, the Stories and Capacity Schedule View shows message "This view is only available if all teams are on the same schedule." Why this message appears when both the teams use scrum and have same sprint length

In JIRA Portfolio, when multiple teams are added, the Stories and Capacity Schedule View shows message "This view is only available if all teams are on the same schedule." Why this message appears when both the teams use scrum and have same sprint length

 

2 answers

1 vote

The message appears if: 

  • Not all teams use the same methodology (e.g. some Scrum some Kanban) 
  • Not all teams use the same sprint length (e.g. 2 weeks vs. 3 weeks) 
  • Not all teams start their sprints on the same weekday 
  • Some teams have custom sprint with a custom name defined (even if they are the same lengths)

Maybe the last point is the reason in your case if all teams are scrum and have the same length: Check in the details view of the teams if there are any custom sprints. If yes, then you'll have to use the "per team" view. 

 

Hi Martin - Radha had filed this query on my behalf.  Let's call these 2 teams T1 and T2.  I've double- and triple-checked that T1 and T2 meet all 4 criteria, specifically:

  1. Team schedule:  Scrum / Iterations
  2. Start:  Monday
  3. Iteration length:  2
  4. Custom Sprints:  7 total (for each), and the NAMES, STARTS and FINISHES for all 7 Sprints are identical for T1 and T2.

So since both teams use Custom Sprints, and per your response it seems that the Capacity View cannot be used if any team uses Custom Sprints (even if they're identically named/starte'd/finish'ed), then  guess we'll have to use the "Per Team" view.  Can you you confirm/refute definitively?

 

Thx!

-Rick

Hello Martin, Can you please answer Rick's question. Thanks for your help!

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

Introducing Advanced Roadmap’s new dependency report

To see this feature in action check out our recent dependencies demo here: https://www.youtube.com/watch?v=eQu5VsUqyZA Keeping on top of your dependencies is a key part of ensuring project success....

150 views 2 6
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you