How should Original Estimates vs. Estimates be used?

How should Original Estimates vs. Estimates be used? Into which column do you put which information? Is it necessary to use both?

1 answer

1 vote
Andy Heinzer Atlassian Team Feb 23, 2018

It is not required to use both.  However when using portfolio, I would probably be more inclined to use the original estimate field when the issue has no estimates at all yet.   This can be useful later on when this issue is then seen by your teams working those issues.  Those team members might adjust the estimate on the issue, or log work against it.   However the original estimate is not expected to change once the issue has started logging work against it, or it exists in an active sprint.   But by using the original estimate field, you can then compare against the other estimate field to see how close you were.

I hope this helps, but in case it does not, perhaps check out this recent blog post about using estimates for Portfolio: Estimation best practices with Portfolio for Jira

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,715 views 23 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you