I'm using a JIRA filter with tasks and stories as the issue soure in my portfolio plan. They're all linked to existing epics. When I go through the plan set up process, it's accurately showing my filter but when the plan gets created, it doesn't show the epics that the stories/tasks are linked to. How can I get all three levels (epic, stories, and tasks) to show up in the plan?

I've also tried using a JIRA filter with just the epics but it's only importing the epics themselves without anything that is underneath them.

1 answer

 

 

 

You have to make sure that your Hierarchy is set properly in Portfolio ->Administration

epics above stories.PNG

So do I have to move it around so that it is set up in this order?...

1. Epic

2. Story

3. Task

(this is the hierarchy I use.)

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,528 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you