I have created a new portfolio plan. Unfortunately user stories which are already in status Done are not included in the plan. Thus any progress on epic level is incorrect.
Is there a way to include completed stories in a portfolio plan?
Your stories are (likely) included in your plan, you just need to make them visible.
This is assuming your issue source is a board or filter based on something simple like:
project = ABC ORDER BY Rank ASC
Here are a few of things to consider:
See https://confluence.atlassian.com/jiraportfoliocloud/tracking-progress-and-status-828785247.html for more information.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The current cloud instance of Portfolio will only include open issues. The inclusion of closed issues has been logged as a suggestion in Atlassian's Jira: https://jira.atlassian.com/browse/JPOCLOUD-1267
Hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.