I have been trying to capacity plan in the new Advanced Roadmaps that replaced Portfolio for Jira and so far I have only been able to get the points vs velocity to show in a 'current sprint' in the roadmap but not in the 'projected sprint'. Any thoughts as to why that might be happening or what I can do different?
Thanks.
Hi Jason,
The estimates allocation vs velocity info is only available for active or future sprints. You can create future sprints in your Jira board and estimate/velocity information would become available in the plan.
Nonetheless, that is a good feature suggestion. I would encourage you to create a suggestion ticket here so other users could comment and vote for it.
I hope that helps, happy to hear your thoughts.
Cheers,
Roi
Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.