Displaying both Target End and Due Date on Portfolio chart

Edited

I would like to show the distinction between Target End date and the Due Date in Portfolio.  My organization is driven by Due Dates, but to plan the team's time effectively, we will want to target early completion.  I know I can change the end of the bar to be Due Date vice Target End and I know how to show the due date as a data field, however, I would like to display both in the Gantt chart.

I think the ideal display would be to use Target Start and Target End for the bar, then use Due Date to put a Diamond or other milestone-like symbol on the bar to show the slack time between when we expect to be done vs the externally required due date.

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Posted in Jira Service Management

Jira Service Management Documentation Opportunities

Hello everyone, Hope everyone is safe! A few months ago we posted an article sharing all the new articles and documentation that we, the AMER Jira Service Management team created. As mentioned ...

286 views 0 7
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you