Can you make timeline on roadmap based on estimation?

Antun Štefančić January 30, 2023

Hello,

So I have the basic roadmap feature, and im interested if its possible to create (automatically ofc.) the timeline for a epic or task or whatever, based on the estimation time, so i dont have to manually choose start and due date to get the timeline.

Also is there an option, for roadmap also, not to count weekends when creating timeline?

 

1 answer

1 accepted

1 vote
Answer accepted
Curt Holley
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 30, 2023

Hi @Antun Štefančić 
The only way (I can think of) to achieve this would be via automation.
Where estimation figure dictates the Due date field entry when compared to whatever baseline start date is used.

Arguably this would be more effort than setting a start and due date...and would depend on where the estimation info is currently stored. 