Log work no longer works by pressing '+' next to Time Tracking

Reuben Sivan December 13, 2012

It works on More Actions->Log Work, but it used to also work by pressing + next to the Time Tracking screen area.

3 answers

1 accepted

0 votes
Answer accepted
Reuben Sivan December 13, 2012

I just got an answer from support, they disabled Tempo and it fixed the issue.

Hi Reuben,

You've run into a bug with Tempo, I've completely disabled Tempo from the UPM and you should be set now.

0 votes
Reuben Sivan December 13, 2012

I am using JIRA on demand, 6.0.

I think the previous one was 5.1.1

0 votes
vkharisma
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 13, 2012

Hey there, which version of JIRA are you using now? and which version it was working before?

Thanks, Vicky