Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How to Edit Original Estimates Properly?

Batuhan Durmaz May 15, 2024

Greetings,

We have multiple projects on Jira.

The working hours of these projects are between 09:00-19:00 (10 hours)

However, in some of our projects 8 hours = 1 day on clockworks, while in some projects 10 hours = 1 day.

How can I organize this ambivalence? Where can I edit it?

1 answer

1 accepted

0 votes
Answer accepted
Ivan Lima
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 15, 2024

Welcome to the Atlassian Community.

The time tracking is global and affects all projects. If you need different configurations for different projects, you will need to manage this through other mechanisms like custom fields or third-party plugins that allow project-specific time tracking settings. See https://support.atlassian.com/jira-cloud-administration/docs/configure-time-tracking/ for more details.

Batuhan Durmaz May 17, 2024

Thank you.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
atlassian, team '25, conference, certifications, bootcamps, training experience, anaheim ca,

Want to make the most of Team ‘25?

Spend the day sharpening your skills in Atlassian Cloud Organization Admin or Jira Administration, then take the exam onsite. Already ready? Take one - or more - of 12 different certification exams while you’re in Anaheim at Team' 25.

Learn more
AUG Leaders

Upcoming Jira Events