What is the correct filter for Portfolio

Deleted user September 19, 2018

I am having an issue where portfolio is trying the schedule tasks that are already done.

I have 3 teams my sources are a board for each team and an overall board

 

The team boards have a filter

"Project = CT and Team = 1"

"Project = CT and Team = 2"

"Project = CT and Team = 3"

and the overall board is 

"Project = CT"

 

Portfolio is trying to schedule Done issues in the future.

I need the Done issue on the team boards otherwise when an issue is moved to Done it will be removed from the scrum board.

Also can Portfolio calculate past velocity if you don't bring in the Done issues.

 

Thanks

 

1 answer

0 votes
Gabriele Franck
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 20, 2018

Hi @[deleted]

In case those Done issues don't have a *resolution* select, Portfolio will not consider them as completed issues and will try to schedule them until you provide a resolution for them.

Could you please double check if this is the problem here? :)

 

Gabi